Montlake
蒙特莱克小学现代化和扩建项目
The existing school building will be modernized and an addition will be built.
蒙特莱克小学已经搬到了约翰·马歇尔学校的临时地点, 520 NE Ravenna Boulevard, 2023-24学年和2024-25学年.
Timeline
- Pre-design phase complete
- Schematic design complete
- 设计开发阶段完成
- 施工文件/许可阶段正在进行中
- Bid and award phase complete
- Construction in progress
- School opens Fall 2025
Project Progress
里程碑达到-封顶仪式
Placing the final beam on a steel structure is celebrated as the “topping out” of a new building. The topping out ceremony for the new addition at Montlake Elementary School took place on Thursday, Mar. 7, 2024. Photos and a video are below.
观看最后一根钢梁安装到位的视频.
Live Video
Construction Photos
Construction Update
进度更新公布了前一个月.
Major activity in March 2024
- 完成的结构钢的增加.
- 为学习平台浇筑混凝土.
- 继续对地标建筑进行现代化改造.
主要活动预计在2024年4月
- 开始建设新的体育馆.
- 开始给新楼装屋顶.
- 继续修建地标性建筑.
- 继续设计新建筑的外部框架.
今年5月,起重机将返回进行一些额外的施工工作.
Current Designs
这些图片展示了建筑师对新学校外观的设计.
Community Participation
虚拟社区更新- 2022年12月
感谢大家在12月11日星期二参加我们的活动. 13.
你可以随时向 Let’s Talk. Select Montlake Construction to ensure it comes directly to the Montlake project team.
学校设计谘询小组(SDAT)
Early in the design process, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, and community members. 学生有时被包括在整个或部分过程中. 项目施工经理也参与其中. 了解更多关于蒙特莱克小学SDAT的信息.
虚拟社区会议- 2022年6月
Thank you to all who could join us for the community update on Thursday, June 2.
Community Update Presentation-June 2022
About the Project
现有的两层教学楼是指定的西雅图地标. The 22,447 square-foot landmarked building will be renovated and modernized.
The proposed design includes renovations to the existing landmarked building and construction of a new 3-story addition.
专为当前和未来的学生
Once complete, the school will provide an equitable learning space for up to 500 K-5 elementary students. It will meet district educational standards while reflecting the input from the school design advisory team comprised of school leaders, students, parents, and community members.
The addition will be set into the site with a roofline height that respects the scale of the current school building and neighborhood.
- Accessibility will be built in throughout the campus to ensure everyone can attend or visit the school.
- Classrooms will be arranged with a variety of shared learning spaces to support academic success for every student.
Safety and security
Students, families, and visitors will be welcomed through a new entry plaza on the northeast side of the of the addition.
游客将通过一个单一的入口进入, the secure main entrance that invites them into the administrative office for check-in before entering the school.
Outdoor connections
New outdoor learning spaces will be constructed on the east side of the landmarked school building. A central play courtyard will provide a direct connection to the garden terraces. A second-floor learning and play terrace will directly connect to classrooms.
建设可持续发展的未来
可持续设计的特点将建立在工作朝着
清洁能源和可再生资源的地区目标, including a high-performing building envelope and the installation of solar panels.
临时搬迁- 2023-24学年和2024-25学年
Montlake Elementary School will move to the John Marshall School interim site, 520 NE Ravenna Blvd, during construction. 学校将提供校车接送.
More information
Design Firm: DLR Group
总承包商/建筑管理公司(GC/CM): Skanska
Project Budget: $64.8 million
Funding Source: Building Excellence V (BEX V) Capital Levy, approved by Seattle voters in 2019.
Project Manager: Paul Wight, pdwight@chippyirvine.com, 206-252-0648