蒙特莱克小学现代化和扩建项目

The existing school building will be modernized and an addition will be built.

蒙特莱克小学已经搬到了约翰·马歇尔学校的临时地点, 520 NE Ravenna Boulevard, 2023-24学年和2024-25学年.

construction phase graphic showing that the school is in the Construction phase
了解在这些项目阶段会发生什么

Timeline

  • Pre-design phase complete
  • Schematic design complete
  • 设计开发阶段完成
  • 施工文件/许可阶段正在进行中
  • Bid and award phase complete
  • Construction in progress
  • School opens Fall 2025

Project Progress

里程碑达到-封顶仪式

Placing the final beam on a steel structure is celebrated as the “topping out” of a new building. The topping out ceremony for the new addition at Montlake Elementary School took place on Thursday, Mar. 7, 2024. Photos and a video are below.

两个人站在一个钢架结构上
钢铁工人等待最后一束-三月. 7, 2024
a person in a safety jacket and hard hat leans forward to write on a white painted steel beam
项目经理保罗·怀特在最后一根横梁上签字. 7, 2024
a short person and a tall person wear construction safety vests and hard hats while standing in front of part of a steel beam painted white. 横梁上写着“谢谢SPS的选民,茱莉亚·皮尔森”
Montlake Principal Julia Pearson and Capital Projects and Facilities Director Richard Best at beam signing – Mar. 7, 2024
2 people stand on a red, white, and blue beam on one corner of a steel framed structure. they are shaking hands. 一端是常青树,另一端是美国国旗.
最后一根梁就位时的祝贺握手-三月. 7, 2024
2个人在顶部的钢结构两侧各搭一个红色, white and blue beam that has an american flag and an evergreen tree on it
钢铁工人把横梁装到位. 7, 2024
a steel beam is being slung into place at the top of a steel framed building by a crane . 两个人在现有结构的顶部等待
在最后的光束中飞行. 7, 2024
a group of people in construction safety vests and hats stand in front of a steel beam with a steel framed structure behind
项目人员与最后的光束- Mar. 7, 2024

观看最后一根钢梁安装到位的视频.

Live Video

Camera 1

Camera 2

Construction Photos

一栋两层砖砌建筑的顶层有窗户. an excavator is sitting below it on a concrete pad with only two walls remaining. 混凝土旁边有个垃圾箱
Demolishing the old gym where it attached to the landmarked building – August 2023
一座两层砖砌建筑的混凝土平台上有东西被移走了
现有户外游乐场拆卸工程正在进行中- 2023年8月
外墙正在施工的砖房
支撑学校现有的西侧- 9. 2023
地面上有材料的建筑工地
建筑南侧挖掘- 9月. 2023
建筑物旁边的建筑工地鸟瞰图
Aerial view in October 2023
a brick building has wood in the window holes and construction next to it
Concrete forms and rebar for new footing next to historic building – Oct. 2023
inside of a building partially torn up with posts and beams with some windows covered in wood and some open
地标建筑一层内部拆除- 10月. 2023
Aerial view of a construction site with a brick building at one end and streets all the way around
工程视图与开挖过程中,面向西北- 11月. 2023
钢筋壕旁边的砖房
混凝土模板工作和新基础的钢筋安置- 11月. 2023
aerial view of a construction site with a brick building at one end and a view of a lake in the distance
西北方向的鸟瞰图- 12月. 2023
at brick building with boarded up windows sits in a construction site with a concrete wall in front
12月,历史建筑西侧混凝土挡土墙完工. 2023
a construction site has a concrete pump truck installing concrete in a form
浇筑混凝土干墙,朝西- 12月. 2023
an excavator sites on dirt with a trench that has wide concrete forms with rebar and concrete pump nozzle leading into it.
泵送混凝土到钢筋混凝土基础形式- Dec. 2023
aerial view of a construction site surrounded by streets and houses with a lake and a stadium in the distance
望北与赫斯基体育场在背景- 2月. 2024
aerial showing a rectangular brick building with construction happening behind it including a crane
Looking east with the landmarked building in the foreground and the new steel structure in progress behind – Feb. 2024
a steel framework for a 3 story building with a crane partially showing in the foreground
新建筑的钢结构安装- 2月. 2024
a long room with rafters showing and a concrete wall next to some windows
Concrete sheer wall for seismic upgrades in the landmarked building – Feb. 2024

Construction Update

进度更新公布了前一个月.

Major activity in March 2024  

  • 完成的结构钢的增加.
  • 为学习平台浇筑混凝土.
  • 继续对地标建筑进行现代化改造.

主要活动预计在2024年4月

  • 开始建设新的体育馆.
  • 开始给新楼装屋顶.
  • 继续修建地标性建筑.
  • 继续设计新建筑的外部框架.

今年5月,起重机将返回进行一些额外的施工工作.

阅读邻里新闻更新

Current Designs

这些图片展示了建筑师对新学校外观的设计.

architect's drawing of a large interior space with a stage and some round tables
对公地和舞台的潜在看法- 2022年10月
带有庭院的u形建筑的平面图
拟建建筑物及现有建筑物的地盘图则- 10月. 2022
建筑师绘制的带有人行道和花园的砖砌建筑
新入口的建筑师图纸- 2023年6月
architect's drawing of a brick building with a courtyard and playground equipment
2023年6月,游戏区域的建筑师图纸

Community Participation

虚拟社区更新- 2022年12月

感谢大家在12月11日星期二参加我们的活动. 13.

社区会议简报

你可以随时向 Let’s Talk. Select Montlake Construction to ensure it comes directly to the Montlake project team.

学校设计谘询小组(SDAT)

Early in the design process, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, parents, and community members. 学生有时被包括在整个或部分过程中. 项目施工经理也参与其中. 了解更多关于蒙特莱克小学SDAT的信息.

虚拟社区会议- 2022年6月

Thank you to all who could join us for the community update on Thursday, June 2.

Community Update Presentation-June 2022

About the Project

现有的两层教学楼是指定的西雅图地标. The 22,447 square-foot landmarked building will be renovated and modernized.

The proposed design includes renovations to the existing landmarked building and construction of a new 3-story addition.

专为当前和未来的学生

Once complete, the school will provide an equitable learning space for up to 500 K-5 elementary students. It will meet district educational standards while reflecting the input from the school design advisory team comprised of school leaders, students, parents, and community members.

The addition will be set into the site with a roofline height that respects the scale of the current school building and neighborhood.

  • Accessibility will be built in throughout the campus to ensure everyone can attend or visit the school.
  • Classrooms will be arranged with a variety of shared learning spaces to support academic success for every student.

Safety and security

Students, families, and visitors will be welcomed through a new entry plaza on the northeast side of the of the addition.

游客将通过一个单一的入口进入, the secure main entrance that invites them into the administrative office for check-in before entering the school.

Outdoor connections

New outdoor learning spaces will be constructed on the east side of the landmarked school building. A central play courtyard will provide a direct connection to the garden terraces. A second-floor learning and play terrace will directly connect to classrooms.

建设可持续发展的未来

可持续设计的特点将建立在工作朝着
清洁能源和可再生资源的地区目标, including a high-performing building envelope and the installation of solar panels.

临时搬迁- 2023-24学年和2024-25学年

Montlake Elementary School will move to the John Marshall School interim site, 520 NE Ravenna Blvd, during construction. 学校将提供校车接送.

More information

Design Firm: DLR Group

总承包商/建筑管理公司(GC/CM): Skanska

Project Budget: $64.8 million

Funding Source: Building Excellence V (BEX V) Capital Levy, approved by Seattle voters in 2019.

Project Manager: Paul Wight, pdwight@chippyirvine.com, 206-252-0648